Texas large-load queue

A historical ERCOT snapshot of large-load applications through 2033, separated by project stage.

Historical snapshot as of 2026-04-26, reviewed 2026-09-06. This page does not claim to show the current queue. Applications include uncertain projects and do not equal realized demand.

445.8 GW of applications in this snapshot

ERCOT April 2026 operational overview, page 4. Values are rounded by the source.
StageGW
No studies321
Under review93.7
Section 9.5 requirements met22
Observed energized5.9
Approved, not operational3.2

What the queue can tell a developer

The largest application bucket has no studies. That separates early requests from projects closer to grid delivery, but does not assign a completion probability. Watch study progress, required network work and the gap between approval and operation.

ERCOT’s observed energized measure uses non-simultaneous peaks for fully operational approved loads. It must not be added to, or compared directly with, the simultaneous EIA hourly grid-demand series.

Original ERCOT April report (PDF) · Stage definitions in the March report · Large-load integration process

Source: ERCOT. Raw data reproduced with attribution; analysis by Compute Current.