FERC docket shows a wave of large-load tariff filings from grid operators and transmission owners
Summary
The Federal Energy Regulatory Commission (FERC) has logged a cluster of tariff proposals on connecting and managing very large electricity customers, according to a combined notice of filings published in the Federal Register on November 23, 2026. The notice lists submissions from the California Independent System Operator Corporation (CAISO), the New York Independent System Operator (NYISO) and several transmission owners. Many of them respond to show cause order EL26-71 or comply with docket EL26-67.
CAISO filed an amendment to an earlier large load filing and resubmitted a large load tariff amendment. NYISO and the New York transmission owners jointly proposed revisions on integrating large loads, effective February 1, 2027. The owners include Central Hudson Gas & Electric, New York State Electric & Gas, Rochester Gas and Electric, Niagara Mohawk Power, Consolidated Edison Company of New York, and Orange and Rockland Utilities. Viridon Path 15, Horizon West Transmission, GridLiance West and Trans Bay Cable each answered the EL26-71 order with tariff changes targeted for February 16, 2027.
Other large-load filings carry proposed effective dates through early 2027. One sets operational requirements and annual reporting for large computational load, starting January 16, 2027. Another covers large load review, cost recovery and transmission services, dated February 14, 2027. A grid responsive integration transmission service is slated for March 16, 2027. The notice does not name the filers for these entries, and two further filings revise transmission owner tariffs to accommodate large load interconnection.
The same notice includes routine items: exempt wholesale generator self-certifications from Circle City Energy Storage, Felix 1 and Travertine Solar; Duke Energy compliance and agreement filings; an amended AEPTX-Coleto Creek Power generation interconnection agreement; and foreign utility company self-certifications from Hesi Renewables, Hexa India Companies and Hexa Japan Companies.
Why it matters
Grid operators and transmission owners in California and New York are converting federal show cause and compliance proceedings into concrete tariff language on how big new loads get studied, connected, charged and operated. One filing explicitly targets large computational load with operating requirements and annual reporting. That points directly at AI and cloud campuses. Developers seeking capacity in these footprints will face new review steps, cost recovery terms and possibly flexible service options. Those rules would take effect between January and March 2027, so they bear on projects now in interconnection queues and on site selection between regions.
Expert Lens
Because so many filings cluster around the same show cause order, FERC appears to be pushing for a broadly consistent large-load framework rather than leaving each utility to set its own rules. Cost recovery provisions likely matter most for developers, since they may shift network upgrade costs or require credit support before service begins. A grid responsive transmission service suggests faster connection could be traded for curtailment obligations. That trade-off would affect backup generation design and how campuses are underwritten. The signal to watch is the protest record in these dockets and whether FERC accepts, rejects or conditions the filings before the early-2027 effective dates.