Large-load tariff filings make grid terms a cost data centers must price
A Federal Register notice lists a run of large-load tariff filings in California and New York with proposed effective dates from 1/16/2027 to 3/16/2027. The connection terms, not just the megawatts, now belong in the site model.

Key argument
Data center buyers in California and New York should treat large-load operating obligations, cost recovery and flexibility terms as priced contract variables now, even though none of the filed tariffs has been accepted.
Between 1/16/2027 and 3/16/2027, a cluster of proposed tariff changes aimed at very large electricity customers would take effect if the Federal Energy Regulatory Commission allows them. The list comes from a combined notice of filings published in the Federal Register on 11/23/2026. The California Independent System Operator Corporation is named as applicant on a resubmitted large-load tariff amendment and on a compliance amendment to that earlier amendment. Elsewhere in the same listing are separate filings on large-load review and cost recovery (proposed effective 2/14/2027), on a grid-responsive integration transmission service (3/16/2027), and one titled "Operational Requirements for Large Computational Load and Annual Reporting" (1/16/2027). In New York, the notice shows the New York Independent System Operator, Inc. filing jointly with six transmission owners, among them Consolidated Edison Company of New York, Inc. and Niagara Mohawk Power Corporation, on integrating large loads, with a requested date of 2/1/2027. Four transmission owners, Viridon Path 15, Horizon West Transmission, GridLiance West and Trans Bay Cable, each answered a show-cause order in docket EL26-71, all asking for 2/16/2027.
My reading is that the terms on which a large computational load connects are moving into filed tariffs. A data center buyer in these two markets should therefore treat operating obligations, cost allocation and flexibility commitments as contract variables with a price, not as background. The evidence has a clear edge. A notice of filings carries titles, some applicant names and requested effective dates. The tariff text that would show what each obligation contains sits in the individual dockets. The notice does not describe what the EL26-71 order required, and it does not say whether the Commission will accept any of these proposals. When I move from filing titles to the substance of the obligations, that step is inference, and I mark it where it happens.
A filing date is not an accepted tariff
The milestone ladder for a tariff runs differently from the one for a power plant, but it is just as strict. A filing is submitted, noticed and opened to comment. After that the Commission accepts it, rejects it, accepts it with conditions, or suspends it and sets it for further process. Only then does an effective date mean anything. Every date in this listing is the applicant's request. The notice spells out that anyone wanting to intervene or protest must do so by the comment date, and that intervention, not a protest alone, is what makes someone a party. Large customers and developers who want a say in these terms have a procedural door, and it closes on a deadline.
Two details in the California entries point to iteration. One filing is labelled a resubmission of a large-load amendment. Another is a compliance amendment to a large-load amendment in an original docket, listed with no effective date. A resubmission can have mundane causes, such as a formatting defect or a docketing correction, so I would not read it as a rejection. What it does show is that the California large-load framework has gone through more than one pass before the Commission, and its final text is not settled. A lender or buyer who models a connection under it is modeling a draft.
Until an order issues, each of these dates is a request.
Two grids writing rules for the same customer
The filings do not describe one framework. In California, the listing splits the subject into at least four strands: review and cost recovery, an operational requirements and reporting regime for large computational loads, a transmission service built around grid responsiveness, and transmission-owner tariff revisions to provide for large-load interconnection, which appear twice. New York arrives as a single joint package from the grid operator and its transmission owners. A separate entry ties large-load tariff revisions to compliance in docket EL26-67, also requested for 3/16/2027.
The compliance labels deserve weight. Under EL26-67, and under the show-cause responses in EL26-71, filers are answering something the Commission started rather than acting purely on their own initiative. The notice does not state what either proceeding requires, so this is an inference: the regulator appears to be pushing transmission owners to write large-load terms down. That shifts leverage. Bespoke service agreements give a large, creditworthy buyer room to negotiate. A tariff gives every comparable buyer the same terms, and it gives the grid operator and transmission owners a filed basis for imposing requirements and recovering costs.
The grid-responsive service runs the other way. Judging only by its title, it may offer an alternative path for loads willing to adjust consumption when the system needs it. That could be the most valuable item in the stack for a buyer racing a delivery date, or it could carry curtailment terms that an inference fleet with tight uptime commitments cannot accept. The title alone does not settle which.
The customer is the same in both markets. The rulebooks are not.
Underwriting a campus against an unsettled tariff
What follows is analysis, not a reading of any tariff text. For a site in either footprint, I would carry three tariff variables in the model instead of one interconnection date. First, does the load face operating requirements and annual reporting, and what would compliance cost in equipment, controls and staff time? Second, under the cost recovery design, who pays for the network upgrades the load triggers, and is that charge up front, over time, or subject to true-up? Third, does a flexible service offer an earlier or larger allocation, and at what curtailment exposure?
For a colocation tenant, the practical step is a diligence question rather than a verdict. Under which tariff regime does the landlord's utility service agreement sit, and do the lease's pass-through clauses reach new charges or obligations created after signing? Answering that needs the actual contract and the accepted tariff, and neither exists yet for these filings. For a lender, the rule is simpler. A load-service date that depends on one of these proposals should not count as firm until the order is issued and the compliance terms are known.
Price the terms first. The megawatts follow.
The case that tariffs only write down existing deals
The strongest objection is that these filings change paperwork, not economics. Large customers already sign service agreements that contain operating limits, upgrade reimbursement and reporting. A tariff that codifies those practices could lower risk by making terms predictable and cutting negotiation time, which helps buyers more than any bespoke concession would. On this view, the grid-responsive service is pure option value: buyers who dislike it decline it, and buyers who need speed take it. The requested dates also sit months out, and the Commission often accepts tariffs with modest changes, so the eventual terms may differ little from current contracts. If that holds, my call to reprice site models overstates the change.
I concede part of this. Predictability has value, and if the accepted text mostly restates current agreements, the cost effect could be small. My thesis narrows to this: the risk lies in not yet knowing the terms, not necessarily in higher cost. I still weight the objection less, because the filing titles point beyond codification. A dedicated operational requirements and reporting regime, a separate cost recovery filing, and compliance proceedings started by the Commission all suggest obligations being defined for this class of load, not merely transcribed. That is an inference from titles. The docket text would confirm or refute it.
Orders that would turn these filings into costs
The first signal is the Commission's order on the California large-load review and cost recovery filing, requested for 2/14/2027. If it is accepted largely as filed, buyers there have a fixed cost allocation rule to model, and upgrade exposure becomes a number rather than a negotiation. If it is suspended or sent to further proceedings, connection economics in that market stay open, and any campus schedule that depends on it should carry a contingency. The notice gives no date for an order.
The second is the content of the operational requirements filing, which is available in the docket. If the requirements amount to annual reporting and load forecasting, the burden is administrative and small. If they include ride-through standards, curtailment obligations or limits on how quickly load can ramp, they reach into electrical design and uptime commitments, and they belong in the capital budget.
The third is how the Commission treats the four transmission-owner responses in EL26-71. If it accepts them, that show-cause proceeding closes and the large-load rules in that part of the grid settle. If it rejects them or demands changes, expect another round of filings, and treat any requested effective date as provisional until a final order issues.
Sources
The Current is written by Josh Jiwoon Inn with AI assistance in drafting. It does not claim interviews or first-hand reporting, and every number is attributed to a named source. See the AI-assisted Disclosure and Methodology.